Payment bond vs performance bond is a common point of confusion, because the two are often bought together on the same construction job. They protect different people against different risks. A performance bond protects the project owner if the contractor fails to finish the work. A payment bond protects subcontractors and suppliers if the contractor does not pay them. This guide explains both in plain English, how they differ, when each is required and how claims work.
This is general information, not legal or financial advice. Bond terms and deadlines depend on the contract and the law of the state where the project is located, so check with a licensed surety agent or attorney before you rely on it.
Key takeaways
- A performance bond guarantees that the contractor will complete the project according to the contract. It protects the owner.
- A payment bond guarantees that the contractor will pay its subcontractors, laborers and material suppliers. It protects them.
- On US federal construction contracts over $150,000, the Miller Act requires both, and each is generally 100% of the contract price.
- Many states have “Little Miller Acts” with similar rules for public projects. Deadlines and notice rules differ by state.
- Both bonds are issued by a surety. If the surety pays a claim, the contractor must repay it. They are a form of credit, not insurance for the contractor.
Payment bond vs performance bond: quick comparison
| Performance bond | Payment bond | |
|---|---|---|
| What it guarantees | The contractor will complete the project as the contract requires | The contractor will pay for labor, materials and equipment |
| Who it protects | Project owner (the obligee) | Subcontractors, laborers and suppliers |
| Who makes a claim | The owner | Unpaid subcontractors and suppliers |
| What triggers a claim | Contractor default, such as abandoning the job or not meeting specifications | Contractor fails to pay a covered party |
| Who pays the premium | The contractor | The contractor |
| Often issued | Together with the payment bond | Together with the performance bond |
What is a performance bond?
A performance bond is a guarantee from a surety company that the contractor will perform the work under the contract. If the contractor defaults, the owner can claim against the bond to cover its loss, up to the bond amount. For a full explanation of parties, cost and the claims process, read our guide to what a performance bond is.
What is a payment bond?
A payment bond is a guarantee from a surety that the contractor will pay the people who supply labor, materials and equipment for the project. If the contractor does not pay a covered subcontractor or supplier, that party can claim against the bond.
Payment bonds matter most on public projects. On private projects, an unpaid subcontractor can usually file a mechanic’s lien against the property. Public property generally cannot be liened, so the payment bond gives unpaid parties another way to recover what they are owed.
How the three parties fit in
- Principal: the contractor who buys the bonds and must do the work and pay its bills.
- Obligee: the project owner, such as a government agency or a company, which requires the bonds.
- Surety: the company that issues the bond and guarantees the contractor’s obligations.
Subcontractors and suppliers are protected by the payment bond but are not parties to the bond itself. They claim as beneficiaries.
When are the bonds required?
Federal construction contracts
The Miller Act requires a performance bond and a payment bond on federal construction contracts over $150,000. Under the Federal Acquisition Regulation, the contractor must furnish them before receiving a notice to proceed. Bidders may also need a bid bond earlier in the process; our guide explains how bid bonds work.
- Performance bond: 100% of the original contract price, plus 100% of any increase. The contracting officer may accept a smaller amount if it adequately protects the government.
- Payment bond: also 100% of the original contract price plus increases. The contracting officer can waive this with a written determination that it is impractical, and the payment bond must be at least as large as the performance bond.
- Contracts from $35,000 up to $150,000: the contracting officer chooses alternative payment protections, such as a payment bond, an irrevocable letter of credit or an escrow arrangement.
State and local projects
Most states have their own versions, commonly called “Little Miller Acts”. They usually require bonds on state-funded and many local public projects, but thresholds, bond amounts and claim deadlines differ. Always check the law for the state where the work is done.
Private projects
No law may require bonds on private work, but owners and lenders can ask for them in the contract, especially on large or risky jobs.
How a payment bond claim works
Rules vary by state and by bond. As an example, here is how the federal Miller Act handles claims:
- Who can claim: anyone who furnished labor or material under the contract and has not been paid in full within 90 days after their last labor or material.
- Direct contract with the prime contractor: may sue on the bond once the 90-day period has passed.
- No direct contract with the prime contractor (for example, a supplier to a subcontractor): must give the prime contractor written notice within 90 days after last providing labor or material, delivered in a way that gives proof of delivery.
- Deadline to sue: within one year after the day the claimant last performed labor or supplied material.
Miss these deadlines and you may lose your right to claim, so act quickly and keep records. State laws have their own timelines, and some are shorter.
Which bond do you need?
| Your role | What matters to you |
|---|---|
| General contractor | You will usually be asked to provide both. Underwriting looks at your credit, finances and experience. |
| Subcontractor | Check whether the project has a payment bond and get a copy. It is your safety net if you are not paid. |
| Supplier | Find out whether a payment bond exists and note the notice deadlines before you ship material. |
| Project owner | Require both bonds on larger projects so that completion and payment of subcontractors are covered. |
What do the bonds cost?
The contractor pays a premium, which is a percentage of the bond amount. The surety sets it based on risk, including the contractor’s credit, financial strength, experience and the size and type of the job. Many sureties quote performance and payment bonds together as a package, but premiums vary widely. Ask a licensed surety agent for a quote for your project.
Small businesses may qualify for help. The SBA’s Surety Bond Guarantee Program backs bid, performance, payment and ancillary bonds issued by participating sureties, for contracts up to $9 million for non-federal work and $14 million for federal work. The SBA fee is 0.6% of the contract price on performance and payment bonds.
Frequently asked questions
Is a payment bond the same as a performance bond?
No. A performance bond guarantees the job will be finished. A payment bond guarantees that subcontractors and suppliers will be paid. They are often issued together.
Do I need both?
On federal construction contracts over $150,000, yes, unless a waiver applies. On other projects it depends on state law and the contract.
Who can claim on a payment bond?
Subcontractors, laborers and suppliers who provided labor or materials to the project and were not paid, within the bond’s and the law’s notice and deadline rules.
Does a performance bond pay unpaid subcontractors?
Generally no. That is the job of the payment bond. A performance bond is focused on completing the project for the owner.
Who pays for the bonds?
The contractor pays the premium, although many contractors build the cost into their bid price.
Are bonds the same as insurance?
No. If a surety pays a valid claim, the contractor has to reimburse it. A bond is a guarantee backed by the contractor’s credit.
In short, the payment bond vs performance bond difference comes down to who is protected: the project owner for performance, and the subcontractors and suppliers for payment. Keep that payment bond vs performance bond rule in mind when you read any contract.